Sarangpur ROB is situated near South side of Kalupur Railway station

Sarangpur ROB is situated near South side of Kalupur Railway station. It connects Ambedkar Chowk to the west & Rakhial Road to the east. In January RLDA has been entrusted to reconstruct nearly 100 yrs old bridge.

After reconstruction lane in the railway portion will be increased to 6. Further it will also connect with upcoming elevated road network of Ahmedabad station this will significantly reduce the traffic congestion in nearby vicinity.

Total span of ROB is divided in 2 phases, approaches & railway span. The length of approaches is 497 Mtr. & length of railway span is 138 Mtr including 107 Mtr Single span Bow string Girder Bridge. Major work of dismantling of approaches and railway span has been completed. Work was challenging as it needs to be carried out in traffic blocks without affecting railway operations.

The works are progressing rapidly, and all the piling works (total 132 nos), 18 pillars out of 23 and and 44 girders out of 76 has been casted. By Tentatively by august 2026 all work will be completed. RLDA is committed to deliver the project in scheduled time duration of 18 months.